Before you start your next bathroom remodel, how much of the job is actually ready to go?
Not just priced. Selections made, materials purchased and either delivered or scheduled to arrive when needed, and subcontractors committed to pricing and scheduling.
Think about plumbing fixtures. You may not need them on day one, but you'll need them just a few days into the project. If they're not selected, purchased, and ready when needed, you're already setting yourself up for delays.
The goal isn't to have 100% of every project ready before starting. That's rarely realistic. But you need a minimum standard.
Here's what I recommend:
Identify early decisions. Know which selections, materials, and trades are needed during the first half of the project.
Set a minimum. Aim to have the first 50% of your schedule covered by completed selections, purchases, and confirmed trade commitments before starting.
Get commitments from trade partners.
Someone needs to drive selections and keep decisions moving.
The bottom line: Delayed decisions should mean a delayed start, not a stalled project.
It's much easier to explain why you're postponing the start date than why a bathroom is torn apart and nobody is working. And remember, even when nobody is working on your job, that job is still costing you money.
Good project management starts before the project does.