Adroit inc town planning and construction, Contact information, map and directions, contact form, opening hours, services, ratings, photos, videos and announcements from Adroit inc town planning and construction,, Construction Company, Room 16, Plumpton Chambers 95H. Chitepo Street Mutare Opposite EcoBank, Mutare.

Fairbridge project Stages: Main house- substructure,  superstructure& timber framework & coveringDuration: 51days
20/08/2026

Fairbridge project
Stages: Main house- substructure, superstructure& timber framework & covering
Duration: 51days



Darlington project 2Stages: Main house- substructure,  superstructure& timber framework & coveringDuration: 35days
18/08/2026

Darlington project 2
Stages: Main house- substructure, superstructure& timber framework & covering
Duration: 35days



Linkroad project 19Stages: setting out, foundation excavation, footing, brickwork, ground beam, backfilling, rumming and...
17/08/2026

Linkroad project 19
Stages: setting out, foundation excavation, footing, brickwork, ground beam, backfilling, rumming and concrete slab.
Duration:11days



Chikanga project 6Stages: superstructure; window level, ring beam & wall plateDuration:10days
17/08/2026

Chikanga project 6
Stages: superstructure; window level, ring beam & wall plate
Duration:10days



Fern valley project 5 Stages: Main house- substructure,  superstructure& timber framework & coveringDuration: 41days
17/08/2026

Fern valley project 5
Stages: Main house- substructure, superstructure& timber framework & covering
Duration: 41days



Linkroad project 18Stages: superstructure; window level, ring beam & wall plateDuration:13days
17/08/2026

Linkroad project 18
Stages: superstructure; window level, ring beam & wall plate
Duration:13days



Linkroad project 17Stages: boundary wall, plastering, floor tiling, plumbing & electrical installation, solar installati...
17/08/2026

Linkroad project 17
Stages: boundary wall, plastering, floor tiling, plumbing & electrical installation, solar installation, painting interior and exterior.
Duration:43days



Chikanga project 7(Mountain Rise)Stages: setting out, foundation excavation, footing, brickwork, ground beam, backfillin...
11/06/2026

Chikanga project 7(Mountain Rise)
Stages: setting out, foundation excavation, footing, brickwork, ground beam, backfilling, rumming and concrete slab.
Duration:15days



Linkroad project 18Stages: setting out, foundation excavation, footing, brickwork, ground beam, backfilling, rumming and...
04/06/2026

Linkroad project 18
Stages: setting out, foundation excavation, footing, brickwork, ground beam, backfilling, rumming and concrete slab.
Duration:17days



Linkroad project 15Stages: window installation, plastering in & out, rough floorsDuration:10days
13/05/2026

Linkroad project 15
Stages: window installation, plastering in & out, rough floors
Duration:10days



Address

Room 16, Plumpton Chambers 95H. Chitepo Street Mutare Opposite EcoBank
Mutare

Opening Hours

Monday 08:00 - 17:00
Tuesday 08:00 - 17:00
Wednesday 08:00 - 17:00
Thursday 08:00 - 17:00
Friday 08:00 - 17:00
Saturday 08:00 - 13:30

Telephone

+263772571724

Alerts

Be the first to know and let us send you an email when Adroit inc town planning and construction, posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Adroit inc town planning and construction,:

Shortcuts

Share