09/10/2026
🔨 DECK MATERIALS ARE IN & LOG SETTING STARTS TUESDAY! 🔨
Larry here with the latest site update from Machias!
Things are moving fast on site:
🪵 Decking Delivered: Deck framing materials are officially on-site, and framing starts this week!
🪵Subfloor Complete: The crew is wrapping up the edges and installing the 1x6 band board around the entire outside perimeter—essential for holding the logs off the floor to fit the finish flooring underneath.
🪵Precision Work: Exactly 802 crush blocks installed in the structure to carry the massive timber weight! 🤯
🪵Lakeside Cleanup: The homeowners were up this weekend clearing brush along the water, and we've set up timelapse cameras to catch the entire build process! 🎥🌅
Next Tuesday is the big day: we start setting logs! Stay tuned for the timelapse footage! Drop a 🪵 in the comments if you're excited to see the logs go up!