Update from the campus steam project.
Mission-critical work: traced a leak on a live 4-inch steam main fed from the central boiler plant, installed isolation valves, shut the section down, and welded in new pipe. Back in service. No leaks.
Boiler work doesn't stop at the plant wall.
Built right. Kept running.