Advon Corporation Project Update: Tampa VAMC Specialty Treatment Expansion 🚧
We are making incredible progress this week on our Specialty Treatment Expansion project at the VAMC in Tampa, FL! Our team has been hard at work hitting key milestones:
- Booster Pump Room: Piping successfully fabricated and installed.
- Water Tower Project: Fully completed in front of the main entrance, and the roadway has been completely restored for smooth access.
- Roofing & Insulation: Continued steady installation of ISO Board, Cover Board, and TPO Membrane on both the North and South walls.
- Rooftop Core Drilling: All core drill locations on the rooftop are now officially complete.
Thank you to our dedicated crew for their hard work and commitment to excellence as we continue shaping this vital healthcare space!