04/09/2026
We poured a pad for the customer to park his boat on. We dug and poured a footing and set the wall forms on day 1. Day 2 we poured the pad with a wall monolithically, and made him a nice 6" curb to stop him from backing off the pad. Day 3 Stripped and finished up the dirt work.
Firm Foundation Concrete provided the labor
Greenup Construction peeled out the grass and dug the footings
Express Mobile concrete provided the concrete