The Finish Line Is Coming Into View at Camp Evergreenπ²ποΈ
The new natatorium at Camp Evergreen is getting closer to the finish line, and the latest progress is bringing the vision into focus.
Inside the facility:
β
Tile work is nearing completion
β
Pool plastering and finish work is underway
β
Doors, windows, drywall and painting are complete
β
HVAC installation is complete
Outside, site concrete work has officially begun and will continue over the next several weeks as the project moves into the final stages.
Itβs exciting to see the details coming together after watching this project grow from the ground up. Each milestone brings Camp Evergreen one step closer to a year-round aquatic facility designed to serve campers, families and the community for generations to come. πββοΈ
And while the construction team continues building toward that future, Camp Evergreen is celebrating 100 years! π
Join them Sunday, October 4, at 3 Sheeps Brewing Company for The Big Splash β a day of live music, food, craft b**r, raffles and plenty of ways to celebrate a century of Camp Evergreen.
Proceeds will support the Natatorium Project and help bring this vision one step closer to reality.
π
Sunday, October 4
π 3 Sheeps Brewing Company
πΆ Evan and Tom Leahy Band | 11 AMβ1:30 PM
π₯ Fire on High | 1:30β5:30 PM
Come celebrate 100 years of Camp Evergreen and help support the next chapter. π²π¦β€οΈ
Learn more about the Natatorium Project: https://campevergreensheboygan.org/natatorium-project/