SEWER CONSTRUCTION IS STARTING!!!

We here on the sewer team hope you had a wonderful summer and are looking forward to fall. With the end of season almost here, it is time to start sewer work here in town. This is our first Facebook post of the season, and we will be posting every Thursday (or sometimes Friday) until work ends in June of 2027. We hope you find these posts informative and helpful while we continue this very important project. Here goes….

While we will not be giving weekly updates on the satellite treatment facility over on Route 6, we do want to give you the current update on how the project went this summer and where we are heading into the fall. The dewatering of the site is still happening, and we expect this to continue until February/March of 2027. They have poured the concrete base mat as well as the lower walls for the Headworks Building. Over the fall and winter they will continue pouring concrete for the remaining lower walls as well as the elevated slabs for the Headworks Building. In the spring of 2027 they will backfill the Headworks Building and start masonry work for the electrical room and chemical storage room. The completion of the satellite treatment facility is on schedule to be completed at the end of 2028/beginning of 2029.

The Central Vacuum Station down on Ryder Street Ext, is still undergoing upgrades even though the structure itself has been complete since last year. This fall and winter they will be installing new sewage pumps, new vacuum pumps, new odor control carbon absorbers as well as electrical upgrades. During this work there will be some planned shutdowns of the vacuum sewer. When this needs to occur there will be ample notification of what this shutdown will entail and what you as residents and business owners will need to do (or not do) during these shutdowns. We will do our best to keep you informed every step of the way as to make the inconvenience short and as easy as possible.

Starting week ending 9/11/26 the Robert B. Our Company will be mobilizing equipment and supplies to the parking spots on Winslow Street. These spots will be coned off in advance, and you can still use the available spots on Winslow Street. RBO will also be doing mark outs on both Jerome Smith Road and Winslow Street.

Starting week ending 9/18/26 and continuing thru mid October, RBO will be doing mark outs, sewer line installation and sewer stub installation on both Jerome Smith Road and Winslow Street. They plan to start at the Jerome Smith end and work their way towards the VMCC. During this work, which will start at 7am and end at 4pm daily, will involve full road closures. You must plan ahead for parking as well as entering or exiting your property during working hours.

The sewer team would like to thank you in advance for your cooperation and understanding during this very important project. If you have any questions or concerns, please call or email Sherry Prada, DPW Deputy Director at 508-487-7060 or [email protected].

Send a message to learn more

09/03/2026

LABOR DAY HOLIDAY SCHEDULE

On Monday September 7th the Department of Public Works will be closed in observance of Labor Day. For those of you who have Monday trash and recycling pickup, your pickup will be on the holiday. Yes, pickup is on Monday September 7th. Please note that the summer holidays are regular days for the Sanitation Team.
The Transfer Station will be open on Monday September 7th but only from 7am to 10:30am. So please plan accordingly.

Thank you for your cooperation. If you have any questions regarding the holiday schedule please call Sherry Prada, DPW Deputy Director at 508-487-7060 or email at [email protected]

Send a message to learn more

DPW SHOUT OUT!!!Even though Provincetown had a huge party yesterday for Carnival, you would not know that this morning! ...
08/21/2026

DPW SHOUT OUT!!!

Even though Provincetown had a huge party yesterday for Carnival, you would not know that this morning! I would like to give a big shout out to the DPW teams who assisted with security, traffic, road closures, bathroom coverage, water and sewer coverage, building clean up, road clean up and of course trash pickup. Thanks to them it does not look like we had a party yesterday! In addition to working all day yesterday, DPW started their day at 2am to complete this major cleanup. So, for that I want to say THANK YOU!!! Thanks to all our staff, we did our part to make carnival a success. See you next year at Cosmic Rodeo!

07/30/2026

HOUSEHOLD HAZARDOUS WASTE DAY!

The second of the three HHW days will be this Saturday August 1st, 2026, and will be held at the Truro Transfer Station, 1 Dump Road (Route 6) in Truro. The event starts at 9:00am and ends at noon. Proof of Provincetown residency will be required. Thank you.

If you have any questions please feel free to call Sherry Prada, DPW Deputy Director at 508-487-7060 or [email protected].

07/20/2026

SHANK PAINTER ONSITE VISITS

The Shank Painter Road project team will be doing onsite visits on Tuesday, July 21st from 8am to noon. The team will start at Bradford Street and Shank Painter and traverse towards Jerome Smith Road. The team will be going over the maps that you were sent and answer any questions you may have.

If you would like the team to stop at your property either keep an eye for the team or call DPW Deputy Director Sherry Prada at 508-487-7060 to be put on the list so we don't miss you. We look forward to seeing you and answering your questions. Thank you.

Send a message to learn more

HELP NEEDED!Today during routine water department work a water department member left a Champion 4000 Watt Generator nea...
07/06/2026

HELP NEEDED!

Today during routine water department work a water department member left a Champion 4000 Watt Generator near the curb where the Towns service truck was located. This was on Bradford Street at 173. Upon returning to his truck the generator was gone. This item was not out for free and belongs to the Town. If you mistakenly took this item, please feel free to return to either the Provincetown Police Department or the DPW main office at 2 Mayflower Street (off Winslow Street), no questions asked.

If you have any questions or concerns or have any information related to this please contact Sherry Prada, DPW Deputy Director at 508-487-7060 or email at [email protected]. Thank you for your help.

07/02/2026

INDEPENDENCE DAY HOLIDAY SCHEDULE

The Department of Public Works will be closed on Friday July 3rd in celebration of Independence Day.

The Sanitation Department will be on regular schedule for trash and recycling pickup on Friday. Please put out your barrels on Thursday evening after 6pm like you normally do.

The Transfer Station will be open on Friday July 3rd on regular schedule and will be open on Saturday July 4th from 7am to 10:30am.

Everyone here at the DPW wishes you all a fun and safe holiday AND stay cool!!! If you have any questions please call or email Sherry Prada, DPW Deputy Director at 505-487-7060 or [email protected].

06/16/2026

JUNETEENTH HOLIDAY SCHEDULE

The Provincetown Department of Public Works office will be closed Friday June 19th in observance of the Juneteenth holiday.

Fridays trash and recycling pickup will be on regular schedule so please pull your barrels curbside Thursday evening after 6pm. The Transfer Station will be open but only from 7am until 10:30am so please plan accordingly.

If you have any questions, please call Sherry Prada, DPW Deputy Director at 508-487-7060 or email at [email protected]. Thank you!

Send a message to learn more

05/21/2026

MEMORIAL DAY HOLIDAY SCHEDULE

On Monday May 25th the Department of Public Works will be closed in observance of Memorial Day. For those of you who have Monday trash and recycling pickup, your pickup will be on the holiday. Yes, pickup is on Monday May 25th. Please note that the summer holidays are regular days for the Sanitation Team.

The Transfer Station will be open on Monday May 25th but only from 7am to 10:30am. So please plan accordingly.

Thank you for your cooperation. If you have any questions regarding the holiday schedule please call Sherry Prada, DPW Deputy Director at 508-487-7060 or email at [email protected] See less

Send a message to learn more

04/30/2026

PAVING OPERATIONS

The Town of Provincetown's Water Department will be paving in various locations next Tuesday May 5th and Wednesday May 6th. You can expect work to start at 7am and to be finished by 4pm on both days. They will have a police detail both days to assist with traffic but you can expect minor detours and delays in areas of work.

If you have any questions, please call or email DPW Deputy Director Sherry Prada at 508-487-7060 or [email protected]. Thank you for your cooperation and patience.

Send a message to learn more

Address

260 Commercial Street
Provincetown, MA
02657

Opening Hours

Monday 7am - 4pm
Tuesday 7am - 4pm
Wednesday 7am - 4pm
Thursday 7am - 4pm
Friday 7am - 11am

Telephone

(508) 487-7060

Alerts

Be the first to know and let us send you an email when Provincetown DPW posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Shortcuts

Share