๐ ICE BARN ADDITION & RENOVATION | PROJECT UPDATE
Progress continues at the Ice Barn Addition & Renovation Project!
Work on the east addition has been moving right along.
๐น Excavation for the east addition is complete
๐น Footings and foundation are in place
๐น Foundation backfill is complete
Over the next phase of the project, crews will be working on:
๐น Underground rough-ins within the east addition foundation
๐น Completion of underground utilities
๐น Sidewalks, curb and gutter
๐น Asphalt paving of the west parking lot
Thereโs still plenty of work ahead, but itโs exciting to see the progress as the project continues to take shape.
We appreciate everyoneโs patience around the construction areas and look forward to sharing more updates along the way!
A big thank you to the Oahe Capitals for trusting us with this project. Weโre proud to be a part of improving a facility that means so much to local hockey players, families, and our community.
Stay tuned for more updates as we keep things moving!