We're taking a look back at one of our completed projects!
📍 Chase Bank – Parmer Ranch | Georgetown, TX
HR Marc completed the earthwork and full site concrete package for this ground-up commercial banking facility. Earthwork included building pad excavation, hauling 550 tons of limestone base, and grading and compacting 400 cubic yards of building pad material in 8-inch lifts. The site concrete scope included the building foundation, paving, sidewalks, ADA ramps, curb, light pole bases, and other site concrete improvements.
Proud to have partnered with Embree Construction Group on another quality project that will serve the Georgetown community for years to come.