08/27/2026
Building Up at Maryland School for the Blind
The Maryland School for the Blind Gym & Pool Project continues to take shape—and there’s a lot happening on site!
• Buildings are progressing upwards
• Gym roof trusses are now in place
• Concrete is being poured for the multi-purpose pool
• BGE has energized the building, marking another important milestone
Each milestone brings us closer to delivering a state-of-the-art facility that will serve Maryland School for the Blind students and the greater school community for years to come.
We’re proud of the progress and grateful to the entire project team working together to make this important project a reality.
MSB Gym and Pool: https://bit.ly/4yfaqjA