Last week we talked about keeping this Overland Park addition from looking like an addition. Hereβs how the sixteen weeks actually ran.
Weeks 1 to 3: prep, demo, planning how the old kitchen would open into the new space. Weeks 4 to 6: framing, structural work, tying the new roof into the existing one. Weeks 7 to 9: electrical, plumbing, HVAC, insulation, drywall. Weeks 10 to 12: ceiling and beams, flooring, cabinets, island. Weeks 13 to 16: counters, tile, appliances, lighting, paint, punch list, done.
Nothing surprising on that list, and thatβs the point.