Merlo crews have been out in force working day and night to get Boynton Bridge project to the finish line. We set 5 prestressed concrete beams on September 17 and returned on September 30 to pull off an impressive 100 cubic-yard deck pour.
Some of you may be wondering about the workers positioned on each side of the abutment as the beams are being set. Their role is to make sure the beams are perfectly placed on the bearing pads and beam seats, which have a precise layout and centerline markings.
Once beams are set, Merlo surveyors record elevations and grades across each beam at specified locations to ensure that the deck pans are installed properly between each beam, and also that a perfect 8” concrete deck can be placed for the bridge. They also consider the camber (upward curvature) of the bridge beams, the load that will be placed on the beams and deck pans, and the final elevation profile after permanent loads are applied.
The finished bridge must be prepared to safely carry vehicles and pedestrians, so precision is a must.