04/27/2021
Project 421 Gateway to Madison full width surface milling will start:
Thursday, 4/29/21, and will be completed by Friday, 4/30/21, on Harrison Street from Fillmore Alley south to Milton-Madison bridge approach and from Baltimore Street west East Street. Construction crews will also complete surface milling for asphalt joints at all intersections / construction limits throughout the project including Fillmore Alley, 1st Street, 2nd Street, Clay Street, Roosevelt Street, Baltimore Street, and SR 56. Surface asphalt over entire project limits will start on Monday, 5/3/21, and be completed in phases through Monday, 5/10/21. No street parking will be allowed on Harrison Street or Main Street between East Street and Milton-Madison bridge and on 2nd Street between Clay Street and SR 56 from 4/29/21 to 5/10/21. The traveling public will experience delays due to local lane closures and flagging in these areas. Your cooperation is appreciated and will ensure expedited completion of the project.