01/26/2024
Taking you behind the scenes of Conchy Joe's Seafood Restaurant addition project with a progress update! Our concrete and masonry subcontractor, Doyle Masonry, has been hard at work on the outside bar component, showcasing the intricate sequence of construction stages.
👷♂️ **Stem Wall Footers:** The foundation begins with the installation of stem wall footers, ensuring a solid base.
🧱 **Stem Wall Block Installation and Grouting:** Next, the stem wall takes shape as blocks are meticulously installed and then the cells grouted for stability.
🚜 **Backfilling the Stem Wall:** With the foundation set, backfilling inside the stem wall is carefully done to prepare for the next phase.
👷♂️ **Forming the Slabs:** Moving upward, the elevated slab is formed over the stem wall along with the slab on grade and then they are poured, creating the floors of the bar structure.
🧱 **Installing Block Walls on Elevated Slab:** The final touch involves installing block walls on top of the elevated slab, shaping the exterior of the bar.
Hats off to Doyle Masonry Inc. for their expertise and getting it done!
Curious about construction sequencing or planning your own project? AEgen Construction is here to guide you. Reach out today! Contact us at 772-302-9529 or [email protected].