06/12/2026
Progress continues on the Summerville Elementary School Addition as the project enters the final stretch! Interior work is now 95% complete, with exterior construction reaching 90% completion. Crews are focused on final sitework, life-safety system testing, and preparations for upcoming inspections. Through strong collaboration with Dorchester School District Two and the design team, the project remains on schedule for staff and students to begin using the new addition at the start of the upcoming school year.โจโจ BuildingTheFuture FoundationsBuiltWithTeamwork