Challenging Project. Tight Timeline. Quality Results.
This 4,500-square-foot project at a cheese processing plant required heavy removal of recently installed coatings that had begun to fail—all within a demanding three-day schedule.
With a large, coordinated crew and specialized removal equipment, our team was able to prepare the surface and complete the new flooring system on time and within budget.
The new system consisted of ¼-inch urethane cement with angular sand for added traction, finished with PIP’s 2000 UR urethane topcoat for long-lasting protection and performance.
When schedules are tight and conditions are challenging, having the right people, equipment, and experience makes all the difference.
Great work by the entire Pro Maintenance team.