06/09/2026
Construction is progressing well at the DHMS Corpus Christi Expansion. This project adds two new bays to the existing service department, expanding the facility's operational capacity and supporting continued growth. The building has been erected, paving is complete, and crews are actively working through MEP finish-out activities. Installation of the crane extension is also underway.
Having completed the original facility in 2015, we're especially proud to return and partner with Doggett once again. It's exciting to see their continued investment in the Corpus Christi community and to help support that growth through this expansion.