02/13/2025
With great collaboration of CCB and LG on another successful project.
Boiler Plant Stack Pad Repair. Togus VA Hospital.
Brief Description: Scope of Work
This project addresses the cracked and spalling concrete that is supporting the 125ft boiler plant stack.
Demo existing concrete pad back to sound concrete based on Engineering Drawings and report findings as demo continues in respect to cracked concrete
Inspect ductwork and install blank if required and remove ductwork from boiler plant building, cap, and infill the building opening with concrete block, insulate and add brick to match.
Add engineered temporary bracing for exhaust silencer tower as defined by project drawings
Testing services for Structural Steel, AISC & AWS certified
Testing services for concrete placement and cylinders taken for compressive strength reporting
Install re-enforcement steel, concrete forms installed, bracing, placement of concrete, protect concrete placed, seal concrete.
Re-install silencer tower lower support legs with new baseplates and weld into place. Inspection of welds, grout baseplates.
Prime and Paint Silencer tower legs that was removed for project.
Remove Temporary Support structure for exhaust tower
Seal concrete pad
Project phasing to allow uninterrupted service for all operations of the Togus Boiler Plant
This project will improve the structural integrity of the existing boiler plant stack pad and will prevent further deterioration of the concrete and reinforcing steel.