08/20/2026
👷♂️ Take a look at the progress of the new Granby North Service Area Water Treatment Plant!
In late July, SGM's Alex Kordick, PE, Senior Engineer on our Water & Wastewater team, led a construction tour of the facility, which is now a little over 50% complete. It's always rewarding to see a project move from design to construction—and even more exciting to see it taking shape.
Designed by SGM, the new treatment plant features ballasted flocculation/clarification, multimedia filtration, and UV disinfection to replace an aging facility while improving system resiliency, reliability, regulatory compliance, and capacity to meet Granby's future water demands.
We'd also like to recognize our project partners, Blythe Group (architect), Brown's Hill (electrical & controls), and Shaner Life Safety, for their collaboration in delivering this important investment for the Granby community.
Learn more about our Water & Wastewater team: https://sgm-inc.com/what-we-do/water-wastewater/