10/09/2026
Week 3 completed of the 18 x 36 addition that includes a sitting room, master suite with vaulted ceiling, walk in closet and master bathroom. O.C.S. along with help from Hartz Construction ( Troy Hartz ), over the course of three weeks took this project from a completed crawl space foundation up to almost completion. At this point, the exterior is complete with exception of gutters and final grading (grading/site work done by NScott Proprty Maintenance). The interior has been through the inspection process for rough framing, rough electrical, rough plumbing, and insulation, all of which passed with no problems. Drywall was hung and got its first coat today. Once drywall finish work is complete, its off to some tile work, buttoning up bathroom, flooring and trim. Not too far from being completed and so far the build has moved along very smooth and steady without any major issues. Will post more pictures once this project is all done.