Redoing a courtyard is one thing. Doing it while the building around it stays fully operational is another.
At eBay's San Jose campus, our team demolished 8,500 square feet of old concrete hardscape and excavated 3,500 square feet of landscaping while protecting the existing trees on site. From there we rebuilt with 4,200 square feet of decorative concrete flatwork in an autumn beige salt finish, 1,000 square feet of pavers in a running bond pattern, and 2,200 square feet of IPE wood decking, plus new planter walls and underground drainage throughout.
The catch: strict noise compliance limited our working hours each day, and the whole job had to hit 100% completion in 40 days. We hit it.