03/29/2026
SARTA Project - Parking & 2nd Driveway Entrance from Gateway Blvd
SARTA - 1600 Gateway Blvd SE, Canton 44707
Phase 1 Preparation
Hillside Lot Clearing - Approximately 2 acres...and approximately 350 - 400 trees to be felled & removed
Tree Service Contracted: Stumpy's Tree Service LLC StumpysTreeServiceOhio.com
Timeline: Project Bid Invitation: 3/19/26
Jobsite Visitation 3/20/26
Contract Award Date 3/24/26
Work Commencement Date 3/25/26
Completion Requirement Date 3/31/26
Crew: 4 - 6 Person Crew
Equipment Mobilized: 1 - 16CY Chip Truck
1 - 1 Ton Dump Truck
2 - Pick Up Trucks
1 - 15" diameter/165HP Bandit Chipper with winch and hydraulics
1 - 90' Tracked Lift - Platform Basket
1 - Avant 765 Material Handler/Loader on Turf Tires
1 - Toro Dingo 400 Mini-Loader
3 - Equipment Trailers
2 - Brush Hogs - Walk Behind
6 - Stihl Chain Saws from 14" to 20" to 36"
2 - Stihl BackPack Blowers
Scope of Work: Brush Hog in between and in conjunction with Avant Material Hanlder
Fell, log & remove between approximately 350 and 400 trees of various sizes
- Notch & drop about 85% of trees & use the Lift for about 15% perimeter trees by wires and fence and road
- Transport felled trees and brush to chipper with Avant Material Handler along with manual labor assist
- Continue brush hog work in tandem with Avant Material Handler - each helping to clear the area to facilitate Sawyer who is dropping trees
- Make in excess of 20 - 25 Brush Dump Runs and 7 - 10 log dump runs
- No Stump Removal work included in this Phase of the Project
- Keep the area 'coned' off and keep area clear of employees, spectators, etc.
- Daily Housekeeping - blow off sidewalks, roadways, etc. and clear and consolidate job site at end of each day
- Total Project - Approximately 5 Crew Days with Overtime
Here are a few photos from Phase One. Mofe to follow as the project ensues...