10/14/2026
Construction at the Wyoming Downs Border Casino continues to move forward, and we’re starting to see the project really take shape.
Our team and subcontractors are advancing several major phases of work at the same time. Eagle Eye Construction has completed the final foundation-wall concrete placement, wrapping up the basement foundation work. Scott Brothers Electric and GW Mechanical, Inc. are nearing completion of their underground electrical and mechanical installations ahead of the final concrete slab pour.
Above ground, Iron Creek Construction is now erecting the structural steel, while Henry Brothers continues work on the storm-drain system and site utilities.
We’re excited to see the progress taking shape and appreciate the work and coordination from every trade partner on site. With more trades scheduled to join the project in the coming weeks, there’s a lot more to come.