PT.2 Footer & Foundation
After excavation is complete, we use our Topcon Construction total station to transfer the building layout into the excavation. This allows us to establish the exact footing locations, offsets, and elevations before the footer crew begins forming. Precision at this stage is critical because every phase that follows depends on the accuracy of the layout.
With the layout established, Precision Footings, LLC installs the Form-A-Drain system and begins forming the footers. Footers are designed to transfer the structural loads of the home into the supporting soil, making proper placement and bearing conditions essential from the start.
Before the foundation walls were poured, we built a temporary access ramp into the excavation so we could utilize our Cat skid loader to place stone backfill around the forms. Planning ahead allows us to complete this work while access is available, rather than trying to move material into a confined excavation after the walls are in place.
Once the main house footers are formed, we excavated the remaining footers for the front porch and garage step-down, maintaining the proper sequence and elevations throughout the project.
After the footers were poured, Keystone Country Concrete Foundations, Inc. formed and poured the concrete foundation walls.
We backfill every foundation with 100% clean stone. Clean stone provides superior drainage, reduces hydrostatic pressure against the foundation walls, and creates a free-draining backfill that minimizes long-term settlement compared to native soils.
To complete this phase, we excavate the outlet for the Form-A-Drain system, providing groundwater with a controlled path away from the foundation. Proper drainage is a critical part of a foundation system designed to perform for decades.