The team at Gallatin has continued advancing the critical path across Cell 6 completion activities, Cell 8 geologic buffer (GB) placement, electrical infrastructure, and miscellaneous utility work throughout the site.
The most significant milestone achieved this month was the completion of the Cell 6 Compacted Clay Liner (CCL) import and HDPE liner installation in mid-September, which cleared the way for geocomposite installation and allowed the team to protect the underlying subgrade from adverse weather conditions. Cell 6 geocomposite installation is expected to be completed in early October.