Project Update!
Since September 2024, the Morse Electric team has been hard at work modernizing the primary electrical infrastructure at Harry Reid International Airport.
This critical project will provide the resilient, high-capacity electrical backbone needed to support the airport’s next generation of infrastructure and operations.
We’re proud to share that the project is now 80% complete, with major milestones already achieved:
• 12,000-volt utility yard fully installed and tested
• Underground duct banks and medium-voltage cables installed
• Construction of both replacement substations complete
• Two new NV Energy feeder connections and redundant radial loop infrastructure underway
Our team is now focused on final finishes, including new security systems, cameras, fire alarm systems, HVAC units, and lighting.
With completion on track for December 2026, we’re proud of the progress our team has made and the role Morse Electric is playing in building reliable infrastructure for the future of Harry Reid International Airport.