H. J. Russell & Company is proud to support delivery of Phase 1 of DFW Airport’s Terminal F as part of the Innovation Next+ design-build joint venture, led by Archer Western and Turner Construction, alongside partners Phillips May and CARCON, with design teams PGAL, Gensler, and GFT. The project includes a nearly 400,000 SF concourse and new Skylink station, marking DFW’s first new terminal in over 20 years. Construction began in 2024, with completion set for 2027.
The team is executing a large-scale modular approach, fabricating six mega-modules offsite and setting them in place along the taxiway. The largest, at 278 by 136 feet and 3,320 tons, sets a new benchmark for terminal expansion. Installed just nine months after groundbreaking, this strategy is accelerating schedule while enhancing safety, quality, and collaboration across the project team.