🚧 Project Progress | JW Marriott Hotel Singapore
Here’s an update on our planter box hacking and demolition works at JW Marriott Hotel Singapore!
Our team has completed the removal of existing plants, soil and electrical appliances, followed by the hacking and demolition of the planter boxes. Site clean-up and the application of waterproofing protection have also been completed.
🧱 Next up: Tile installation!
Our team continues to carry out each stage with care, ensuring proper site protection and safety throughout the works.
Stay tuned for more updates as we make progress on this project!