30/03/2026
🏗️ 𝐌𝐄𝐆𝐖𝐀𝐑𝐃 𝐂𝐎𝐍𝐒𝐓𝐑𝐔𝐂𝐓𝐈𝐎𝐍 DESIGN & BUILD PROCESS (Step-by-Step guide on what to expect when you engage our construction services)
1. Project Inquiry & Client Briefing
• Meet client and gather requirements:
• Purpose (residential, commercial, fit-out, etc.)
• Budget range
• Lot details / unit size
• Target completion date
• Site inspection (if applicable)
• Initial feasibility check (zoning, access, utilities)
👉 Output:
• Project brief
• Rough budget range
⸻
2. Conceptual Design Phase
• Prepare:
• Space planning
• Initial layout / floor plans
• Basic 3D perspective (optional but recommended)
• Align design with budget (very important in D&B)
👉 Output:
• Concept drawings
• Initial cost estimate (ROM – Rough Order of Magnitude)
⸻
3. Design Development
• Refine approved concept:
• Architectural plans (detailed)
• Structural concept
• Basic MEPF (Mechanical, Electrical, Plumbing, Fire)
• Material selection (tiles, finishes, fixtures)
👉 Output:
• Developed drawings
• Updated cost estimate (more accurate)
⸻
4. Detailed Engineering & Construction Drawings
• Complete full set of plans:
• Architectural
• Structural (with calculations)
• Electrical layout
• Plumbing & sanitary
• Fire protection
• Coordination between all disciplines (avoid clashes)
👉 Output:
• Issued-for-permit drawings
• Detailed Bill of Quantities (BOQ)
⸻
5. Permits & Approvals
• Secure permits based on local codes (e.g. following National Building Code of the Philippines):
• Building permit
• Electrical permit
• Sanitary/plumbing permit
• Fire safety clearance
• Liaise with LGU and regulatory agencies
👉 Output:
• Approved permits
• Authority to construct
⸻
6. Final Costing & Contract Signing
• Submit:
• Final quotation (based on detailed plans)
• Project timeline (Gantt chart)
• Agree on:
• Payment terms (mobilization, progress billing)
• Scope of work
• Contract signing
👉 Output:
• Signed Design & Build Agreement
⸻
7. Pre-Construction Phase
• Mobilization planning:
• Site clearing
• Temporary facilities
• Safety setup
• Procurement of materials
• Final scheduling
👉 Output:
• Construction schedule
• Mobilization readiness
⸻
8. Construction Phase
Typical sequence:
1. Site works / excavation
2. Foundation
3. Structural works
4. Masonry
5. Roofing
6. MEPF installation
7. Finishes (tiles, paint, ceiling, etc.)
8. Fixtures & equipment
• Continuous:
• Quality control
• Cost monitoring
• Progress reporting
👉 Output:
• Physical project completion (substantial)
⸻
9. Testing, Commissioning & Punchlisting
• Test systems:
• Electrical
• Plumbing
• HVAC (if any)
• Identify defects (punchlist)
• Rectify issues
👉 Output:
• Completed, functional project
⸻
10. Project Turnover
• Deliver:
• As-built plans
• Warranties
• Operation manuals
• Final inspection with client
👉 Output:
• Turnover certificate
• Project acceptance
⸻
11. Post-Construction Support
• Warranty period (typically 6–12 months)
• Maintenance support if included