From Kaitaia to Invercargill, our teams are busy doing what we do best: restoring confidence in construction! Time to roll call some of our projects:
Kaitaia Hospital - Stage 1, the Theatre Block, is finished, with work underway on the General Ward Block (Stage 2) and the General Practice, Outpatients and ED Block (Stage 3).
26 Hobson Street - Progress continues on the comprehensive roof replacement, with the building fully covered, providing a protected environment for the installation of the new long-run roofing system and associated remedial works to the facade.
Bunnings Warehouse Taupo – We have just hit an important milestone with the first stage of structural steelwork being installed for this new 9000m2 warehouse facility.
Dannevirke District Court – The building has donned the Brosnan-white shrink-wrap as we take off its old roof and give it a brand-new one.
Rolleston College – We are on programme, with the main structure to be completed in the next 2 weeks, and the final main concrete pour happening soon.
Aurora College – With our team fully mobilised on Blocks 1 and 2, cladding and internal work are well underway.