09/08/2023
Recently we assisted March Cato in installing a new sewer line that connects to the Rosedale wastewater plant, and it's been quite the undertaking.
March Cato has been utilising tunnel boring to excavate tunnels underground and installing pipes within them.
They have also been completing open cuts by thrusting the pipe through the newly built underground hole created by the tunnel boring device.
Meanwhile, our team has been assisting by creating shafts and constructing pads for the heavy machines to go on, as well as helping with open cuts and supporting the tunnel boring machine as needed.
The main challenge we encountered was dealing with unpredictable weather,
In addition to the technical aspects of the project, we've also placed a strong emphasis on safety, ensuring that our workers are protected at all times. This has required careful planning, scheduling, and communication with local authorities to minimise any potential risks.
This new sewer line will have on the community by providing reliable wastewater management and reducing the risk of environmental pollution.
We're proud to have played a part in this essential infrastructure project.