23/06/2026
WHY THE PEOPLE OF ADU–KADZANDANI ROAD SHOULD APPRECIATE THIS PROJECT
As the contractor undertaking the improvement works on the Adu–Kadzandani Road, we would like to provide clarification on the scope of works and the achievements made so far.
First, it is important to understand that the contract was for the grading of approximately 6.5 kilometres of road. The gravelling component was not intended for the entire road length. The contract specifically provided for "patch murram" works, meaning that only selected sections of the road identified as critical were to receive gravel.
At the commencement of the project, the condition of the road was extremely poor. Many sections had deteriorated significantly, making transport difficult for motorists, boda boda operators, school-going children, farmers, and the entire community. In fact, the road had gone for approximately three years without grading, leading to severe surface deterioration.
According to the contract documents, only about 800 metres of the road was earmarked for gravelling. However, in the spirit of serving the community and improving accessibility, we went beyond the minimum contractual requirements by utilizing available resources to patch and improve additional sections of the road and nearby access roads where possible.
The project has achieved the following:
✔ Restoration of the road surface through grading.
✔ Improved accessibility for residents and road users.
✔ Reduced vehicle operating costs and travel time.
✔ Enhanced drainage through culvert installation and drainage improvements.
✔ Additional patch gravelling beyond some of the specified sections.
✔ Improved safety and passability during both dry and rainy seasons.
We also acknowledge that there remains a section requiring gabion works to permanently address drainage and erosion challenges. However, gabion construction was not included in the original contract scope and Bill of Quantities. Such works would require separate design, approval, and funding.
While no project is ever perfect and infrastructure improvements are always a continuous process, we are proud of the work delivered under the available budget and contractual scope. The transformation from the road's previous condition to its current state is evident to anyone who uses it regularly.
Development is achieved step by step. What has been completed is a significant improvement compared to the condition that existed before the project commenced. We therefore thank the residents of Adu, Kadzandani, and the surrounding areas for their cooperation and support throughout the implementation period.
Dachim Investment Limited
Tangible Solutions.