At Astrum, steady progress continues across every stage of construction, with structural and internal development works moving ahead with precision and consistency.
Here’s the latest update:
* RCC work completed up to the 22th floor slab, structural work for the terrace floor slab is underway
* Waterproofing work completed up to 17th floor
* Electrical wall work completed up to 17th floor
* Window frame and shutter work completed up to the 11th floor
* Lift lobby flooring completed up to the 15th floor
* Water supply work completed up to 16th floor
* Plumbing work completed up to the 17th floor