31/07/2026
π§ One Month On Site β Costco Norwich π§
Friday marked our first full month on site delivering the new Costco development in Norwich for RG Carters β and what a month it's been.
A huge amount of work has been completed in a short space of time, which is a real credit to everyone involved.
A special thank you to our partners JJMac for working alongside us to deliver the earthworks and ground stabilisation on this challenging, congested site, and to SDS for their continued work installing the stormwater attenuation.
In just four weeks we've achieved:
βοΈ 12,000mΒ³ of topsoil excavated and removed from site
βοΈ 24,000mΒ³ of on-site subsoil cut and moved, creating 20,000mΒ³ of engineered fill
βοΈ 12,500mΒ² of warehouse floor slab formation stabilised to achieve a 30% CBR, followed by 100mm of Type 1 sub-base
βοΈ 2,130mΒ³ of stormwater attenuation excavated and installed, with a further 2,200mΒ³ currently under construction
βοΈ 420m of deep drainage installed to depths of up to 4 metres
With the programme moving at an exceptionally fast pace, every day counts. The commitment, planning and teamwork shown by everyone on site has been outstanding, and it's the reason we've achieved so much in just four weeks.
A huge thank you to our team and supply chain partners for their continued hard work. We look forward to sharing more progress as the project continues.