26/07/2026
Progress Update – Today
Today’s works focused on earthworks and site preparation. The excavation and formation of the new access track continued, with material being cut and moved to establish the required levels and profile.
A significant amount of soil and spoil has been excavated and stockpiled along the site, while the track area has been cleared and shaped. The excavated route is now clearly established, with further grading and levelling still required.
Today’s progress:
Continued excavation and removal of earth.
Stockpiled excavated material on site.
Progressed formation of the access track.
Carried out initial grading and levelling.
Cleared vegetation and debris from the working area.
Continued shaping the route to prepare for the next stage of works.