03/02/2026
We completed a commercial BMS electrical installation within a hospice environment as part of a wider boiler plant replacement project.
A key challenge with projects of this type is transitioning from old to new systems without disrupting building operation. In this case, the existing boiler system was fully decommissioned while the new plant and BMS infrastructure were brought online, with no downtime during the changeover.
From an electrical and controls perspective, this required careful sequencing of works. New containment routes, power supplies, control panels, and field wiring were installed and tested in advance, allowing the new system to be commissioned before the final switchover.
The scope included installation of a new Hager three-phase distribution board, a Medem gas safety system for monitoring and automatic isolation, and a fully rewired, custom-built BMS control panel to suit the new plant arrangement.
The images show the completed containment, panels, and plant connections, all installed with safe access, maintenance, and future operation in mind.
Works completed on behalf of