25/08/2026
/Single ply warm roof installation completed.
The client has had two recent ‘new roof’s done in GRP fibreglass which had both failed.
One roof built on top of another.
We ripped everything off as shown the boards are saturated.
/All new timber firrings cut on site,
/18mm ply wood
/V***r control layer
/150mm kings pan insulation
/Completed with a sarnafil single ply system.
Full CPS certified certificate given on completion✅
✉️[email protected]
🌎www.michaelenglishroofing.com