16/10/2026
Day 5 of job in Newcastle County Down for Caolin and Niamh, complete excavation of front, back and both sides of the garden. ( 1st photo's before and after) Removing of 55 Tonne of old tarmac, flagstones, soil and general debris. Bringing in hardcore and 44 Tonne of Paving and 20 Tonne of topsoil. We then laid terrapave rimmi ground 600mx400m Flagstones, with a border of charcoal paviors each side of the pathway and Patio area, all of the Flagstones were half bonded on the Patio area. We have 4 new gulleys and 1 recessed manhole cover. With 2 new back steps into the house, plus 1 new step into the garage to be completed, along with the rest of the Flagstones to be laid. We also have 190sqm of new Evergreen Elite Lawn, which is laid on 60mm of Paving grit for drainage purposes, on top of the new topsoil we brought in for the Landscaping work.
More photo's of completed project next week.