27/08/2026
Sloane Square | Where Each Level Stands
Eight townhouses, retained façade, and a lot happening behind it all at once.
At roof level, the mansards are fully prepped, membranes, battens and counter battens all in, ready for slates to go on before the leadwork and flashings finish it off.
At first floor, the rear façade is fully closed up. Brickwork's complete, insulation and vapour control membranes are in, and fireboarding is done at ceiling level, all ahead of first fix electrical.
At basement level, internal partitions are going in on a metal track system, giving the first real sense of how these spaces will divide and function.
Built to EnerPHit standard throughout.
Contractor: LTS
Structural Engineers: Form Structural Design
Services Consultants: Mantis Energy Ltd
CDM Consultant: Goddard Consulting
Interior Designer: Finchatton