A nice little summer house base constructed in Headcorn.
- Hand dug down 200mm at the deepest point, leveling off the ground.
- Spread, levelled and compacted a primary type 1 subase, capped with a 15mm soft sand blinding to ensure the DPC membrane doesn't get pierced.
- Install a DPC Membrane and build the shutter
- Pour the concrete with a layer of A142 reinforced mesh
- Finish off with an Easy float finish and a bullnose trowel edging.
- Final clear and tidy from site