2A Electrical Engineering Services

2A Electrical Engineering Services Contact information, map and directions, contact form, opening hours, services, ratings, photos, videos and announcements from 2A Electrical Engineering Services, Electrician, 105 BOUNCES Road, London.

Work Report: Overhead Metal Trunking Installation in a Robot Work AreaProject Overview• Scope of Work: Installation of o...
08/03/2026

Work Report: Overhead Metal Trunking Installation in a Robot Work Area
Project Overview
• Scope of Work: Installation of overhead metal trunking to facilitate cable management between gates in a fenced robotic work area.

Job Description: The task involved diagnosing and repairing an electrical issue related to a single socket used by the c...
08/03/2026

Job Description: The task involved diagnosing and repairing an electrical issue related to a single socket used by the customer for their washing machine.
It was determined that there was an overload in the single socket used by the customer for the washing machine. The necessary tests were performed for this. It was seen that the cable was not made completely tight and that this was the reason for such a problem. After the MCB safe isolation was done from the fuse box, the socket with the overload sign was replaced with a new single socket. Checks were made with a socket tester and it was tested that the Zs values were appropriate.
Issue Identified: Upon inspection, it was determined that an overload had occurred in the single socket, causing visible damage. The necessary electrical tests were conducted to analyze the issue thoroughly. It was observed that the cable connections were not properly tightened, leading to the electrical fault.

Job Description:The task involved fitting a Steel Wire Armoured (SWA) cable gland to ensure mechanical protection, strai...
08/03/2026

Job Description:
The task involved fitting a Steel Wire Armoured (SWA) cable gland to ensure mechanical protection, strain relief, and a secure electrical connection for a 6mm² SWA cable in an industrial setup. The job required precision in handling, stripping, and terminating the cable to meet electrical safety standards. The process included cable preparation, gland fitting, earthing, and termination into a distribution enclosure.

Job DescriptionThe work involves first-fix electrical installation including:● Running electrical cabling through timber...
12/02/2026

Job Description
The work involves first-fix electrical installation including:
● Running electrical cabling through timber stud framing

● Mounting back boxes

● Drilling and fixing to masonry

● Referencing and adhering to manufacturer documentation

● Working at height using a step ladder






19s

To safely terminate and connect conductors for socket outlets.To ensure correct polarity and secure electrical connectio...
12/02/2026

To safely terminate and connect conductors for socket outlets.

To ensure correct polarity and secure electrical connections.









Job Overview:The objective of this task was to install and terminate a CAT6 Ethernet cable with RJ45 connectors to ensur...
09/08/2025

Job Overview:
The objective of this task was to install and terminate a CAT6 Ethernet cable with RJ45 connectors to ensure a secure and stable network connection for outdoor camera . The termination process follows the industry-standard TIA/EIA-568B wiring scheme for proper signal transmission and minimal interference.
________________________________________
Tools & Equipment Used:
• Cable Stripper – To remove outer insulation from CAT6 cable.
• Cable Cutter – To cut excess wire.
• Crimping Tool – To secure RJ45 connectors onto wires.
• Punch Down Tool – For keystone jacks or patch panels (if applicable).
• RJ45 Connectors (8P8C) – For terminating the CAT6 cable.
• Cable Tester – To verify continuity and performance.

🛠️ Rack Cabinet Installation | 📡 Access Point Setup | 🔌 Patch Panel Termination—Neat. Structured. Future-ready. ✅Our lat...
28/07/2025

🛠️ Rack Cabinet Installation | 📡 Access Point Setup | 🔌 Patch Panel Termination

Neat. Structured. Future-ready. ✅
Our latest network infrastructure deployment features:
✔️ Precision-installed rack cabinet
✔️ Seamless AP mounting for optimal Wi-Fi coverage
✔️ Clean and labeled patch panel termination for easy management

No mess, no guess — just solid connectivity.

1. Description of Work:An inspection and testing procedure was carried out on the consumer unit and associated electrica...
04/05/2025

1. Description of Work:
An inspection and testing procedure was carried out on the consumer unit and associated electrical circuits. The primary focus was to diagnose and rectify an earth fault affecting the ring circuit supplying the flat sockets. The customer, a professional photographer, reported ongoing issues with electronic devices. Their technical service advised checking the power sockets and grounding system to ensure proper installation and function.

2. Fault Identified:
Issue:
A continuity test revealed that there was no continuity between the earth conductors in the consumer unit and the sockets on the ring circuit.
Further investigation identified that multiple earth cables were loose within socket outlets, leading to a loss of proper earthing.
This posed a potential safety hazard, increasing the risk of electric shock and improper circuit protection operation.

3. Testing & Diagnosis:
Continuity Test: No continuity detected between the consumer unit and socket earth connections.
Socket Tester Check: Incorrect wiring indication at affected sockets.
Visual Inspection: Loose earth conductors at socket terminals.
Multifunction Tester Readings: High resistance observed on earth path.

4. Remedial Work Performed:
Re-secured all loose earth connections within socket outlets.
Verified and tightened earth terminations in the consumer unit.
Conducted a retest to ensure full continuity of the earth conductor.
Performed final testing using a socket tester, confirming correct wiring configuration.

5. Final Test Results:
Continuity Restored: Earth connection confirmed at all sockets.
Insulation Resistance Test: Passed.
Polarity Check: Correct.
Earth Fault Loop Impedance: Within acceptable limits.

6. Conclusion & Recommendations:
The issue of loose earth cables within the flat socket ring circuit has been resolved. The system now meets safety requirements. It is recommended to periodically inspect electrical terminations to prevent similar faults in the future.
Supporting Evidence:
Before and after images of the installation.
Electrical testing results confirming proper operation.
Safe isolation procedure documentation.
Client Confirmation: The customer was informed about the issue and the steps taken to resolve it. They confirmed that the washing sockets were now operating safely and efficiently.

Plan, prepare and install:There were several different control measures before starting work, these included: ensuring t...
04/05/2025

Plan, prepare and install:

There were several different control measures before starting work, these included: ensuring there was a permit to work in place prior to the start of the task; where there is restricted access, manlift may be used and must have up to date inspection in place. We had to wear PPE on this site. Helmet protection during works, gloves were to be worn where handheld plants are being used. We also had to wear boots and hi-vis. I have an attached copy of the risk assessment and method statement for this job.

All materials, tools and equipment were stored in a safe, stored onsite. We also had a site box to store our tools in, whilst all the materials were on shelving.

Project Summary: Cable Tray and Data Cabling Installation

In this project, the installation of cable trays and data cabling was carried out. The scope included the setup of 41 access points, 30 data points, and 4 rack cabinets, in addition to a general rack cabinet located in the system room.

Preparation Phase

Data Cabling Planning:

Preparations for data cabling began with analyzing the project design and conducting field measurements. Based on these inputs, the required cable quantities were calculated and ordered.

Labeling:

All access and data points were labeled on the cables according to the numbering system defined in the project plan.

Ex*****on Phase

Team Coordination:

The tasks were divided and organized among team members for efficient workflow.

Equipment Utilized:

Side cutters and cable ties were used for securing cables.

A man lift was employed to access the cable trays, as they were installed on high ceilings.

Cable Pulling:

Using the equipment, the cables were pulled and routed through the cable trays. Different cable lengths were left for access points and data points, with the measured cable lengths generally ranging from 60 to 80 meters.

The project was executed with careful planning and teamwork, ensuring that all cabling met the required specifications and was installed efficiently.

Cctv System &Commercial Audio Systems Wall Mount Speakers Installations.
04/05/2025

Cctv System &Commercial Audio Systems Wall Mount Speakers Installations.

Installation new chandelier light . Faulty switch light found and fixed.Replaced faulty overload double socket outlet.Re...
07/10/2024

Installation new chandelier light . Faulty switch light found and fixed.

Replaced faulty overload double socket outlet.

Replaced by new GU10 led light bulbs .

Core drilling for extractor fan installation.

Address

105 BOUNCES Road
London
N98LE

Alerts

Be the first to know and let us send you an email when 2A Electrical Engineering Services posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to 2A Electrical Engineering Services:

Featured

Share

Category