Enable

Enable Creating infrastructure solutions with lasting community value

๐’๐ฆ๐š๐ซ๐ญ๐ž๐ซ ๐š๐œ๐œ๐ž๐ฌ๐ฌ, ๐ฌ๐š๐Ÿ๐ž๐ซ ๐๐ž๐ฅ๐ข๐ฏ๐ž๐ซ๐ฒ: ๐“๐ก๐ž ๐€๐ฉ๐ฌ๐ฅ๐ž๐ฒ ๐„๐š๐ฌ๐ญ๐ž๐ซ ๐๐ฅ๐จ๐œ๐ค๐š๐๐žโฃโฃโฃโฃWhile many of us were enjoying the long Easter weekend, ou...
17/04/2026

๐’๐ฆ๐š๐ซ๐ญ๐ž๐ซ ๐š๐œ๐œ๐ž๐ฌ๐ฌ, ๐ฌ๐š๐Ÿ๐ž๐ซ ๐๐ž๐ฅ๐ข๐ฏ๐ž๐ซ๐ฒ: ๐“๐ก๐ž ๐€๐ฉ๐ฌ๐ฅ๐ž๐ฒ ๐„๐š๐ฌ๐ญ๐ž๐ซ ๐๐ฅ๐จ๐œ๐ค๐š๐๐žโฃโฃ
โฃโฃ
While many of us were enjoying the long Easter weekend, our site teams executed a massive logistical effort at Apsley station. Operating under a collaborative 'one team' approach alongside Principal Contractor Taziker, we delivered critical Access for All (AfA) foundation upgrades for Network Rail.โฃโฃ
โฃโฃ
Delivering deep foundations and extensive trenching in tight station environments normally relies heavily on expensive On Track Plant (OTP) to shift machinery. It reduces valuable possession time and adds logistical risk. We wanted a smarter, safer approach.โฃโฃ
โฃโฃ
Collaborating early in the planning phase, Enable Design and Enable Infrastructure worked with equipment supplier Cordek Ltd to engineer a bespoke Polybridge and Alimat temporary access solution.โฃโฃ
โฃโฃ
We completed a rigorous temporary works assessment for the station's Harp & Slab construction. The temporary access solution we designed and built enabled us to safely distribute heavy plant weight without touching the track.โฃโฃ
โฃโฃ
Overall, the delivery teams achieved:โฃโฃ
โฃโฃ
โ€ข ๐‡๐ž๐š๐ฏ๐ฒ ๐…๐จ๐ฎ๐ง๐๐š๐ญ๐ข๐จ๐ง๐ฌ: 18 x 300mm diameter, 14-metre deep CFA piles sunk across Platform 4 and the P2/3 island, followed by initial 1-metre lift pit excavations once cured.โฃโฃ
โ€ข ๐‚๐จ๐ฆ๐ฉ๐ฅ๐ž๐ฑ ๐‚๐ข๐ฏ๐ข๐ฅ๐ฌ: 60 metres of buried Cubis multi-duct and 7 chambers installed directly on Platform 4, with all paving slabs and yellow lines fully reinstated for passengers.โฃโฃ
โ€ข ๐™๐ž๐ซ๐จ ๐Ž๐“๐ ๐ƒ๐ž๐ฉ๐ž๐ง๐๐ž๐ง๐œ๐ฒ: All rigs mobilised, grout pumped, and spoil removed using the Polybridge system, keeping heavy machinery entirely off the track space.โฃโฃ
โ€ข ๐’๐ž๐š๐ฆ๐ฅ๐ž๐ฌ๐ฌ ๐ƒ๐ž๐ฅ๐ข๐ฏ๐ž๐ซ๐ฒ: Underpinned by excellent HSEQS management, continuous track monitoring was maintained throughout. The site was fully cleaned down and handed back four hours ahead of schedule.โฃโฃ
โฃโฃ
Johnathan Reid, Enable Infrastructure Contracts Manager, said: "The Easter blockade at Apsley was a real testament to preparation and teamwork. Weeks of work went into getting the site ready. The unseen, less glorified but equally important parts of delivery. During the blockade, piling was delivered seamlessly, and despite late scope changes, the team adapted and over-delivered against plan. The commitment shown by our teams was exceptional, and I want to wholeheartedly thank everyone who gave up their Easter to deliver this scheme."โฃโฃ
โฃโฃ
Andrew Chan, General Manager of Enable Design, added: "By innovating a practical access solution upfront, the team bypassed traditional site complications and delivered a complex civil scope safely within a tight possession window."โฃโฃ
โฃโฃ
A massive thank you to everyone across 342 individual shifts who gave up their Easter holiday to drive these station upgrades forward.โฃโฃ
โฃโฃ
Look forward to our forthcoming technical case studies that detail and explore our work on this programme.

๐Ÿ’œ ๐‡๐š๐ฉ๐ฉ๐ฒ ๐ˆ๐ง๐ญ๐ž๐ซ๐ง๐š๐ญ๐ข๐จ๐ง๐š๐ฅ ๐–๐จ๐ฆ๐ž๐งโ€™๐ฌ ๐ƒ๐š๐ฒ!โฃToday we celebrated the brilliant women across Enable with a small gesture of appreci...
04/03/2026

๐Ÿ’œ ๐‡๐š๐ฉ๐ฉ๐ฒ ๐ˆ๐ง๐ญ๐ž๐ซ๐ง๐š๐ญ๐ข๐จ๐ง๐š๐ฅ ๐–๐จ๐ฆ๐ž๐งโ€™๐ฌ ๐ƒ๐š๐ฒ!โฃ

Today we celebrated the brilliant women across Enable with a small gesture of appreciation - flower bouquets for every woman in the head office ๐Ÿ’ (as seen in the images!)โฃ

Thank you for the impact you make every day.โฃ

๐„๐ง๐š๐›๐ฅ๐ž ๐„๐ง๐ž๐ซ๐ ๐ฒ ๐‚๐จ๐ง๐ง๐ž๐œ๐ญ๐ข๐จ๐ง๐ฌ ๐ฌ๐ญ๐š๐ซ๐ญ๐ฌ ๐ฐ๐จ๐ซ๐ค ๐จ๐ง ๐–๐ž๐ฌ๐ญ ๐’๐ฎ๐ฌ๐ฌ๐ž๐ฑ ๐๐„๐’๐’ ๐๐ซ๐จ๐ฃ๐ž๐œ๐ญโฃMajor progress at Halewick Lane, near Worthing, where ...
11/02/2026

๐„๐ง๐š๐›๐ฅ๐ž ๐„๐ง๐ž๐ซ๐ ๐ฒ ๐‚๐จ๐ง๐ง๐ž๐œ๐ญ๐ข๐จ๐ง๐ฌ ๐ฌ๐ญ๐š๐ซ๐ญ๐ฌ ๐ฐ๐จ๐ซ๐ค ๐จ๐ง ๐–๐ž๐ฌ๐ญ ๐’๐ฎ๐ฌ๐ฌ๐ž๐ฑ ๐๐„๐’๐’ ๐๐ซ๐จ๐ฃ๐ž๐œ๐ญโฃ

Major progress at Halewick Lane, near Worthing, where Enable teams - Enable Energy Connections, Enable Resourcing, Enable Hire & Welfare - are delivering critical enabling works for a Battery Energy Storage Scheme (BESS) in partnership with West Sussex County Council.โฃ

This programme of works will unlock renewable energy storage capacity for local communities for decades to come, building a resilient foundation for clean, accessible energy. โฃ

๐Ž๐ฎ๐ซ ๐ฌ๐œ๐จ๐ฉ๐ž ๐ข๐ง๐œ๐ฅ๐ฎ๐๐ž๐ฌ: โฃ

๐ƒ๐ž๐ฌ๐ข๐ ๐ง & ๐’๐ญ๐ซ๐š๐ญ๐ž๐ ๐ฒ โฃ

- Full design delivery from Enable Design (RIBA Stages 1-4) โฃ
- Comprehensive battery specification and procurementโฃ

๐‚๐ข๐ฏ๐ข๐ฅ ๐„๐ง๐ ๐ข๐ง๐ž๐ž๐ซ๐ข๐ง๐  & ๐ˆ๐ง๐Ÿ๐ซ๐š๐ฌ๐ญ๐ซ๐ฎ๐œ๐ญ๐ฎ๐ซ๐ž โฃ

- Complete access road construction โ€“ breaking down, crushing, and re-laying materials on-site โฃ
- Drainage infrastructure and kerb installation with retaining walls โฃ
- South Gate installation to facilitate circular site access โฃ
- Ducting installation for mains connection to the future switch roomโฃ

๐„๐ฅ๐ž๐œ๐ญ๐ซ๐ข๐œ๐š๐ฅ ๐ƒ๐ž๐ฅ๐ข๐ฏ๐ž๐ซ๐ฒ โฃ

- Full electrical design, installation, and final commissioningโฃ

๐’๐ข๐ญ๐ž ๐’๐ฎ๐ฉ๐ฉ๐จ๐ซ๐ญ & ๐‘๐ž๐ฌ๐จ๐ฎ๐ซ๐œ๐ž๐ฌ โฃ

- Specialist labour supply from Enable Resourcing โฃ
- Full site welfare and logistics provided by Enable Welfareโฃ

๐‹๐ข๐Ÿ๐ž๐œ๐ฒ๐œ๐ฅ๐ž ๐’๐ฎ๐ฉ๐ฉ๐จ๐ซ๐ญโฃ

- Provision of a two-year Operations & Maintenance (O&M) packageโฃ

Over the course of 2026, we are set to deliver a dedicated compound for battery units, PCS units, and the switch room itself, as the CAD imagery โ€“ created by Enable Design โ€“ illustrates.โฃ

Projects like Halewick Lane show how infrastructure and energy transition go hand in hand and fulfil our mission to create infrastructure solutions with lasting community value.

๐๐ซ๐จ๐ฃ๐ž๐œ๐ญ ๐’๐ฉ๐จ๐ญ๐ฅ๐ข๐ ๐ก๐ญ: ๐„๐ง๐ ๐ข๐ง๐ž๐ž๐ซ๐ข๐ง๐  ๐„๐ฑ๐œ๐ž๐ฅ๐ฅ๐ž๐ง๐œ๐ž ๐ข๐ง ๐ญ๐ก๐ž ๐‹๐ข๐ฏ๐ž ๐‘๐š๐ข๐ฅ ๐„๐ง๐ฏ๐ข๐ซ๐จ๐ง๐ฆ๐ž๐ง๐ญ ๐Ÿš‡๐Ÿ—๏ธโฃNavigating the constraints of a live rail cor...
02/02/2026

๐๐ซ๐จ๐ฃ๐ž๐œ๐ญ ๐’๐ฉ๐จ๐ญ๐ฅ๐ข๐ ๐ก๐ญ: ๐„๐ง๐ ๐ข๐ง๐ž๐ž๐ซ๐ข๐ง๐  ๐„๐ฑ๐œ๐ž๐ฅ๐ฅ๐ž๐ง๐œ๐ž ๐ข๐ง ๐ญ๐ก๐ž ๐‹๐ข๐ฏ๐ž ๐‘๐š๐ข๐ฅ ๐„๐ง๐ฏ๐ข๐ซ๐จ๐ง๐ฆ๐ž๐ง๐ญ ๐Ÿš‡๐Ÿ—๏ธโฃ

Navigating the constraints of a live rail corridor demands a unique blend of precision, logistical agility, and geotechnical expertise.โฃ

Our delivery of the Dollis Hill Retaining Wall for Transport for London London Underground remains a benchmark for how we approach these complex structural challenges.โฃ

Working within metres of the operational Metropolitan and Jubilee lines, the project required the replacement of a failing masonry structure with a robust King Post Wall - executed with zero safety incidents and zero service disruption.โฃ

๐“๐ž๐œ๐ก๐ง๐ข๐œ๐š๐ฅ ๐‡๐ข๐ ๐ก๐ฅ๐ข๐ ๐ก๐ญ๐ฌ: โฃ
โœ… Precision Delivery: Installation of 24x 600mm augured King Posts to 12m depth in a highly constrained site. โฃ
โœ… Asset Protection: Management of critical "Tall Plant Approvals" (TPAs) and extensive monitoring of neighbouring structures. โฃ
โœ… Digital Trust: Utilisation of SymTerra provided real-time visibility, ensuring total transparency throughout the build. โฃ
โœ… Complex Remediation: Safe management of hazardous ground conditions to leave a clean, resilient asset.โฃ

Dollis Hill serves as a prime case study in how Enable Infrastructure de-risks complex schemes to protect critical transport assets.โฃ

๐Ÿ‘‰ Explore the full technical case study: https://www.enable-infrastructure.com/projects/dollis-hill-replacement-retaining-wall/

๐ŸŽ„ Merry Christmas from the Enable team!2024 has been quite the year - 40th anniversary โœ…, brilliant projects โœ…, and an a...
24/12/2025

๐ŸŽ„ Merry Christmas from the Enable team!

2024 has been quite the year - 40th anniversary โœ…, brilliant projects โœ…, and an absolutely chaotic game of The Traitors that had the whole office on edge right up to the Christmas party finale ๐ŸŽญ

There was murder. There was mayhem. There were accusations. And yes, the Traitors won. (We're still not over it.)

Beyond the drama, we're proud to have raised money at our Christmas party for Southwark Food Bank - supporting our local community where it matters most ๐Ÿ’š

Wishing you all a wonderful festive season and a brilliant 2025!

Trust no one. Except Santa. ๐ŸŽ…

๏ฟฝ๏ฟฝ ๐„๐ง๐š๐›๐ฅ๐ž ๐„๐œ๐ก๐จ ๐ฅ๐š๐ฎ๐ง๐œ๐ก๐ž๐ฌ ๐Ÿ๐ข๐ซ๐ฌ๐ญ ๐ž๐๐ข๐ญ๐ข๐จ๐ง!The very first issue of the Enable Echo is LIVE โ€“ and for the first time, weโ€™re of...
27/11/2025

๏ฟฝ๏ฟฝ ๐„๐ง๐š๐›๐ฅ๐ž ๐„๐œ๐ก๐จ ๐ฅ๐š๐ฎ๐ง๐œ๐ก๐ž๐ฌ ๐Ÿ๐ข๐ซ๐ฌ๐ญ ๐ž๐๐ข๐ญ๐ข๐จ๐ง!

The very first issue of the Enable Echo is LIVE โ€“ and for the first time, weโ€™re offering an exclusive insight into how we deliver on our mission to create lasting community value.

From rail upgrades and eHGV charging rollouts to ecological innovation and leadership development, this deep dive newsletter is packed with real case studies, industry-leading innovations, and stories from the people powering progress.

๏ฟฝ ๐‡๐ข๐ ๐ก๐ฅ๐ข๐ ๐ก๐ญ๐ฌ:
๏ฟฝ Our 40th anniversary!
๏ฟฝ ยฃ659k of social value delivered in 2024
๏ฟฝ Blackwall DLR, Nissan eHGV Charging, Reading Independent Feeder โ€“ DONE
๏ฟฝ 90% carbon emission reduction on innovative Lot 9 project
๏ฟฝ T-Level programme success + leadership development
๏ฟฝ Meet the new teams and colleagues shaping the UK's energy future
๏ฟฝ What's to come in the future!

๏ฟฝ ๐‘๐ž๐š๐ ๐›๐ž๐ฅ๐จ๐ฐ ๐ง๐จ๐ฐ | ๏ฟฝ ๐…๐จ๐ฅ๐ฅ๐จ๐ฐ ๐Ÿ๐จ๐ซ ๐ฆ๐จ๐ซ๐ž
https://www.enable-team.com/about/newsletter/

๐„๐ง๐š๐›๐ฅ๐ž ๐ˆ๐ง๐Ÿ๐ซ๐š๐ฌ๐ญ๐ซ๐ฎ๐œ๐ญ๐ฎ๐ซ๐ž ๐’๐ฎ๐œ๐œ๐ž๐ฌ๐ฌ๐Ÿ๐ฎ๐ฅ๐ฅ๐ฒ ๐‚๐จ๐ฆ๐ฉ๐ฅ๐ž๐ญ๐ž๐ฌ ๐Œ๐š๐ฃ๐จ๐ซ ๐’๐จ๐ก๐จ ๐„๐Œ๐” ๐“๐ซ๐š๐ข๐ง ๐ƒ๐ž๐ฉ๐จ๐ญ ๐๐ซ๐จ๐ฃ๐ž๐œ๐ญโฃโฃWe're delighted to announce that Enable...
21/11/2025

๐„๐ง๐š๐›๐ฅ๐ž ๐ˆ๐ง๐Ÿ๐ซ๐š๐ฌ๐ญ๐ซ๐ฎ๐œ๐ญ๐ฎ๐ซ๐ž ๐’๐ฎ๐œ๐œ๐ž๐ฌ๐ฌ๐Ÿ๐ฎ๐ฅ๐ฅ๐ฒ ๐‚๐จ๐ฆ๐ฉ๐ฅ๐ž๐ญ๐ž๐ฌ ๐Œ๐š๐ฃ๐จ๐ซ ๐’๐จ๐ก๐จ ๐„๐Œ๐” ๐“๐ซ๐š๐ข๐ง ๐ƒ๐ž๐ฉ๐จ๐ญ ๐๐ซ๐จ๐ฃ๐ž๐œ๐ญโฃ
โฃ
We're delighted to announce that Enable Infrastructure successfully completed Phase 2 of the Soho EMU Train Depot Controlled Emission Toilet (CET) System project for our client West Midlands Trains. Starting in July 2024 and concluding earlier this year, we've delivered all eight walkways on time and to specification, fulfilling our commitment as Principal Contractor.โฃ
โฃ
The project presented significant challenges, including redesigns of track drainage systems and walkways, value engineering exercises, and local restrictions. Through determination and expertise, and collaboration with our client and end users, our team overcame these obstacles and delivered exceptional results. A standout achievement was saving our client ยฃ1.3 million on walkway materials alone through innovative value engineering.โฃ
โฃ
๐ˆ๐ฆ๐ฉ๐ซ๐ž๐ฌ๐ฌ๐ข๐ฏ๐ž ๐๐ซ๐จ๐ฃ๐ž๐œ๐ญ ๐’๐œ๐จ๐ฉ๐ž:โฃ
- Installed 500 meters of deep drainage and 1,300 meters of walkwaysโฃ
- Placed 240 bollard/lighting bases and 40 CET basesโฃ
- Constructed 8 UTX chambers, 11 CET chambers, and 25 manhole chambersโฃ
- Installed 210 meters of drip traysโฃ
- Poured 300 cubic meters of concrete and utilised 100 tonnes of reinforcementโฃ
- Laid 1,200 meters of C/1/9 troughs and 600 meters of C/1/43 troughsโฃ
- Used 800 tonnes of Type 1 infill and 200 tonnes of ballast fillโฃ
- Removed 1,600 tonnes of spoil and 800 tonnes of concreteโฃ
โฃ
๐Ž๐ฏ๐ž๐ซ๐œ๐จ๐ฆ๐ข๐ง๐  ๐‚๐จ๐ฆ๐ฉ๐ฅ๐ž๐ฑ ๐‚๐ก๐š๐ฅ๐ฅ๐ž๐ง๐ ๐ž๐ฌ:โฃ
All work was completed while maintaining depot operations at all times, requiring careful planning of phased possessions and isolations. The team successfully managed a height-restricted access bridge at the main entrance through strict supervision and planning.โฃ
โฃ
This project showcases the power of our integrated approach, with multiple Enable companies working together seamlessly:โฃ
โฃ
- Enable Hire & Welfare providing plant and toolsโฃ
- Enable Welfare delivering welfare facilities and power supplyโฃ
- Enable Resourcing supplying all labour requirementsโฃ
- Enable Design handling temporary works and as-builtsโฃ
- Enable Power Systems managing earthing, bonding, and M&E designโฃ
โฃ
By delivering all project objectives, we've demonstrated our commitment to overcoming complex challenges through collaboration, innovation, and determination. We're proud of our team's achievements and strong collaborative partnership with West Midlands Trains.

๐€ ๐–๐š๐ซ๐ฆ ๐’๐œ๐จ๐ญ๐ญ๐ข๐ฌ๐ก ๐–๐ž๐ฅ๐œ๐จ๐ฆ๐ž: ๐„๐ง๐š๐›๐ฅ๐ž ๐’๐œ๐จ๐ซ๐ž๐ฌ ๐ข๐ง ๐†๐ฅ๐š๐ฌ๐ ๐จ๐ฐโฃ โฃโฃWe're delighted to announce the opening of our new Glasgow office -...
19/11/2025

๐€ ๐–๐š๐ซ๐ฆ ๐’๐œ๐จ๐ญ๐ญ๐ข๐ฌ๐ก ๐–๐ž๐ฅ๐œ๐จ๐ฆ๐ž: ๐„๐ง๐š๐›๐ฅ๐ž ๐’๐œ๐จ๐ซ๐ž๐ฌ ๐ข๐ง ๐†๐ฅ๐š๐ฌ๐ ๐จ๐ฐโฃ
โฃโฃ
We're delighted to announce the opening of our new Glasgow office - expanding our presence across the UK at an exciting time for Scottish infrastructure.โฃโฃ
โฃโฃ
And what a week to make it official! With Scotland dramatically securing their World Cup spot last night, it feels like the perfect time.๏ฟฝ๏ฟฝโฃโฃ
โฃโฃ
Our Glasgow team, headed up by Lee Hollywood Contracts Manager Scotland, will be delivering the same full-spectrum infrastructure solutions that Enable is known for, now with a stronger local presence to serve our Scottish clients and partners better.โฃโฃ
โฃโฃ
Here's to new beginnings, dramatic victories, and building infrastructure that lasts.โฃโฃ
โฃโฃ
Welcome to the Enable family, Glasgow.โฃโฃ

๐ŸŽ‰ ๐Ÿ’๐ŸŽ ๐˜๐ž๐š๐ซ๐ฌ ๐จ๐Ÿ ๐‹๐ž๐ ๐š๐œ๐ข๐ž๐ฌโฃ ๐ŸŽ‰  โฃThis week marks a milestone we're incredibly proud of - Enable's 40th anniversary.โฃ โฃFrom ou...
07/11/2025

๐ŸŽ‰ ๐Ÿ’๐ŸŽ ๐˜๐ž๐š๐ซ๐ฌ ๐จ๐Ÿ ๐‹๐ž๐ ๐š๐œ๐ข๐ž๐ฌโฃ ๐ŸŽ‰
โฃ
This week marks a milestone we're incredibly proud of - Enable's 40th anniversary.โฃ
โฃ
From our origins as BCM in 1985, focused on rail and transport construction and engineering, to becoming Enable, a full-spectrum infrastructure services group, our journey has been defined by evolution, expertise, and the trust our clients place in us.โฃ
โฃ
Four decades of progress. Hundreds of projects delivered. One enduring commitment: creating infrastructure solutions with lasting community value.โฃ
โฃ
To our clients, partners, and the talented, hardworking people who make Enable what it is today - a Team of Teams - thank you for being part of our story.โฃ
โฃ
Here's to the next 40 years of building legacies that matter.

Happy Halloween! ๐Ÿ‘ป๐Ÿฆ‡๐ŸŽƒWe decided to immortalise our brand in pumpkin flesh this year... with a significant anniversary soo...
31/10/2025

Happy Halloween! ๐Ÿ‘ป๐Ÿฆ‡๐ŸŽƒ

We decided to immortalise our brand in pumpkin flesh this year... with a significant anniversary soon to arrive โŒ›4๏ธโƒฃ0๏ธโƒฃ๐ŸŽ†

Address

1st Floor, 57-59 Great Suffolk Street
London
SE10BB

Opening Hours

Monday 8am - 5pm
Tuesday 8am - 5pm
Wednesday 8am - 5pm
Thursday 8am - 5pm
Friday 8am - 5pm

Alerts

Be the first to know and let us send you an email when Enable posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Enable:

Featured

Share