Enable

Enable Creating infrastructure solutions with lasting community value

05/06/2026

On 2026, Olubukola Olose engaged in a discussion with three of our senior leaders Daniel Wiscombe, Andrew Chan & Peter Milnes about Enable's initiatives to meet our environmental and sustainability goals now and in the future.

๐’๐ฆ๐š๐ซ๐ญ๐ž๐ซ ๐š๐œ๐œ๐ž๐ฌ๐ฌ, ๐ฌ๐š๐Ÿ๐ž๐ซ ๐๐ž๐ฅ๐ข๐ฏ๐ž๐ซ๐ฒ: ๐“๐ก๐ž ๐€๐ฉ๐ฌ๐ฅ๐ž๐ฒ ๐„๐š๐ฌ๐ญ๐ž๐ซ ๐๐ฅ๐จ๐œ๐ค๐š๐๐žโฃโฃโฃโฃWhile many of us were enjoying the long Easter weekend, ou...
17/04/2026

๐’๐ฆ๐š๐ซ๐ญ๐ž๐ซ ๐š๐œ๐œ๐ž๐ฌ๐ฌ, ๐ฌ๐š๐Ÿ๐ž๐ซ ๐๐ž๐ฅ๐ข๐ฏ๐ž๐ซ๐ฒ: ๐“๐ก๐ž ๐€๐ฉ๐ฌ๐ฅ๐ž๐ฒ ๐„๐š๐ฌ๐ญ๐ž๐ซ ๐๐ฅ๐จ๐œ๐ค๐š๐๐žโฃโฃ
โฃโฃ
While many of us were enjoying the long Easter weekend, our site teams executed a massive logistical effort at Apsley station. Operating under a collaborative 'one team' approach alongside Principal Contractor Taziker, we delivered critical Access for All (AfA) foundation upgrades for Network Rail.โฃโฃ
โฃโฃ
Delivering deep foundations and extensive trenching in tight station environments normally relies heavily on expensive On Track Plant (OTP) to shift machinery. It reduces valuable possession time and adds logistical risk. We wanted a smarter, safer approach.โฃโฃ
โฃโฃ
Collaborating early in the planning phase, Enable Design and Enable Infrastructure worked with equipment supplier Cordek Ltd to engineer a bespoke Polybridge and Alimat temporary access solution.โฃโฃ
โฃโฃ
We completed a rigorous temporary works assessment for the station's Harp & Slab construction. The temporary access solution we designed and built enabled us to safely distribute heavy plant weight without touching the track.โฃโฃ
โฃโฃ
Overall, the delivery teams achieved:โฃโฃ
โฃโฃ
โ€ข ๐‡๐ž๐š๐ฏ๐ฒ ๐…๐จ๐ฎ๐ง๐๐š๐ญ๐ข๐จ๐ง๐ฌ: 18 x 300mm diameter, 14-metre deep CFA piles sunk across Platform 4 and the P2/3 island, followed by initial 1-metre lift pit excavations once cured.โฃโฃ
โ€ข ๐‚๐จ๐ฆ๐ฉ๐ฅ๐ž๐ฑ ๐‚๐ข๐ฏ๐ข๐ฅ๐ฌ: 60 metres of buried Cubis multi-duct and 7 chambers installed directly on Platform 4, with all paving slabs and yellow lines fully reinstated for passengers.โฃโฃ
โ€ข ๐™๐ž๐ซ๐จ ๐Ž๐“๐ ๐ƒ๐ž๐ฉ๐ž๐ง๐๐ž๐ง๐œ๐ฒ: All rigs mobilised, grout pumped, and spoil removed using the Polybridge system, keeping heavy machinery entirely off the track space.โฃโฃ
โ€ข ๐’๐ž๐š๐ฆ๐ฅ๐ž๐ฌ๐ฌ ๐ƒ๐ž๐ฅ๐ข๐ฏ๐ž๐ซ๐ฒ: Underpinned by excellent HSEQS management, continuous track monitoring was maintained throughout. The site was fully cleaned down and handed back four hours ahead of schedule.โฃโฃ
โฃโฃ
Johnathan Reid, Enable Infrastructure Contracts Manager, said: "The Easter blockade at Apsley was a real testament to preparation and teamwork. Weeks of work went into getting the site ready. The unseen, less glorified but equally important parts of delivery. During the blockade, piling was delivered seamlessly, and despite late scope changes, the team adapted and over-delivered against plan. The commitment shown by our teams was exceptional, and I want to wholeheartedly thank everyone who gave up their Easter to deliver this scheme."โฃโฃ
โฃโฃ
Andrew Chan, General Manager of Enable Design, added: "By innovating a practical access solution upfront, the team bypassed traditional site complications and delivered a complex civil scope safely within a tight possession window."โฃโฃ
โฃโฃ
A massive thank you to everyone across 342 individual shifts who gave up their Easter holiday to drive these station upgrades forward.โฃโฃ
โฃโฃ
Look forward to our forthcoming technical case studies that detail and explore our work on this programme.

Address

1st Floor, 57-59 Great Suffolk Street
London
SE10BB

Opening Hours

Monday 8am - 5pm
Tuesday 8am - 5pm
Wednesday 8am - 5pm
Thursday 8am - 5pm
Friday 8am - 5pm

Alerts

Be the first to know and let us send you an email when Enable posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Enable:

Shortcuts

Featured

Share