Powering Lincoln City Football Club for the season ahead ⚡
Straight after the final whistle of last season, our team was straight to work on a major electrical infrastructure upgrade at Lincoln City FC's stadium.
The scope: removing three legacy supplies and installing a new 550kVA supply with new submains and switchgear around the stadium. Our engineers carried out a full study of the existing distribution network and worked alongside colleagues at National Grid to design the upgrade the club needed.
This gave the stadium the capacity for growth, including a 400A supply to the Rilmac Stand, ready to feed the new fan zone facility and commercial kitchen as part of the wider Imp Territory project; another huge part of this summer's programme at the club.