28/03/2023
Last weeks job, new gas pipework installed at Rocols manufacturing site just up the road from us Swillington.
We changed a 60m section of pipe from a local butterfly valve on the shop floor which fed the plant room and a lever valve to the main offices.
J&C Pipework Limited re routed the new line over a few days, got it prepared ready for the final connection and decommission of the existing pipe. This way there was minimal disruption by not having to turn the gas off until the final day.
On the final day we came in, decommissioned the old pipe work with nitrogen, strength tested the new line with air, purged gas through with our GEA purge kit and finally tightness tested. All appliances re lit and everything back up and running.
🦉 🟡