Treatment plant & surface water installation for 3 log cabins completed recently on some challenging terrain. A vertical drop of approximately 16/17 metres over a distance of 35 metres, crossing a road, several BT cables, some live and some disused, buried HV supply cables, service cables, a water pipe and plenty of rock for good measure. Plenty of backdrop chambers for the sewer to take up the change in elevation. Have really enjoyed this one and the challenges it's brought, havnt enjoyed so much the walking up and down the hill countless times a day to reach an item that is only a few metres away in distance but takes a scramble on all fours to reachđź’¨
All material had to be kept off site at bottom of the hill due to lorries not being able to reach and/or tip/turn on the terrain. Approximately 500t of material excavated, moved and imported to make room for this one