One of our jobs this week was this one: quite a large groundscrew base with an included floor frame.
Our client had three reasons for choosing groundscrews for his combined shed and music room.
Speed - we were in, job done, and out again in only 1 day and the floor frame is immediately ready to build onto. No waiting for concrete to go off, and.....
Cleanliness - we didn't chew up his garden, and there was no concrete to spill on his drive, or the road.
And the slope - so, as you come out of the clients back door, the back garden slopes from the house backwards and from left to right. If a concrete base had been laid it would have formed a dam across his garden so in the winter wet season, the rain would run down his garden, meet with the concrete base, and run off toward his garage. The garden would be a running, swampy river that would be likely to flood the garage. Groundscrews are typically installed to just above the highest point so any rainwater can just run straight under his shed without making the floor wet.
But what about the cost? The whole of this base project came to around £3,500 +VAT. If concrete had been used (forget about the mess) our client would have had three chaps on site for 3 days. he would have had skips, permits, a shuttering, and concrete to pay for, plus he would still need to spend out for a floor frame - but that floor frame would have been in ground contact and more susceptible to rot.
Groundscrews. they're faster, usually cheaper, and a lot more environmentally friendly than concrete.