20/06/2021
Steel work.
A few snap shots of the work that went into this floor.
This floor needed some complicated steel work to ensure its integrity for years to come.
All the shaped rebar was done onsite.
The first smaller rooms are a suspended concrete floor construction, the larger room is a raft construction and the long snake looking thing is 1 of 2 ground beams fitted.
For the full process of this job check out the highlights of 'the lodge' ππΌ.