03/06/2026
Big dig out completed this week for Mullis Construction ๐ช
โ
Site clearance
โ
120t reduce dig & muck away
โ
Footings dug and prepped
โ
20mยณ of concrete poured
โ
30t of Type 1 supplied and installed
Another solid push from the team, keeping everything moving in-house from dig out to muck away and aggregates ๐โ๏ธ