10/10/2026
We are now getting progress again on both jobs , the last 2 weeks we have at Barrhead
fitted wallplate , headbinder and erected the bryce roof , erected and completed the kit. We have fitted and fixed down the 3 block wallplate and loaded in gf panels ready for erection(waiting on scaffolding)
Jackton
We erected the moncrief kit and finished it. Fitted logan wall plate , built headbinder up on boxes, erected roof, erected kit and completed.
We are now well in on the next two wallplates , headbinders and roofs which are a darroch and an evan , comeend of play monday we will be sitting waiting on scaffolding 🫣 or we will have to get next plots roof materials in.
SOME TEAM 🔨